SO CAL EDISON’S
TOPANGA underground utility DISTRICT project
SO CAL EDISON’S
TOPANGA underground utility DISTRICT project

Schedule
January 2011:
Topanga Town Council Project Presentation
March-April 2011: Draft Environmental Study Complete
Project Communication to Local Residents and Organizations
April-May 2011:
Public Comment Period on Draft Environmental Study
Public Open House
July 2011:
County Board of Supervisors Public Hearing, and Approval of Environmental Study and Project
Summer 2011-Spring 2012:
Project Engineering Design Work
Fall 2012:
Complete Engineering Design and Obtain Related Approvals
Winter 2012-2013:
Project Contractor Bidding and Award Process
Spring 2013:
Begin Construction
Fall 2014:
Complete Construction